City Creek gets updated finish: 2012

Published: Wednesday, March 19, 2008 12:22 a.m. MDT
RELATED CONTENT |  E-MAIL | PRINT | FONT + - 
An updated timeline calls for landscapers to be putting the finishing touches on City Creek Center by mid-2012.

Bishop H. David Burton, presiding bishop of The Church of Jesus Christ of Latter-day Saints, met Tuesday with the Salt Lake City Council to summarize the momentum of the estimated $1.5 billion project and present a completion schedule for the downtown mixed-use development.

"You can see that a lot of progress is being made," Bishop Burton said, "and a lot of activity is going forward."

The presentation focused more on the residential component of the project than recent meetings between city leaders and City Creek Reserve Inc., a development arm of the LDS Church.

As many as 900 residential units will be added to the three downtown blocks bordered by West Temple, South Temple, 200 East and 100 South, Bishop Burton said. CCRI officials estimate that people will be able to start moving into the mostly upscale housing units in early 2010.

Residential towers 6 and 7, located on South Temple mid-block between West Temple and Main Street and overlooking Temple Square, will be the first to be completed, Bishop Burton said.

The concrete foundation was poured last weekend for the tallest of the development's residential buildings — a 32-story tower on the southeast corner of West Temple and South Temple. That building, known as tower 1, will have 185 residential units when it opens in early 2011.

Story continues below
Bishop Burton announced a change of plans for the other residential building on the former Crossroads Plaza block, tower 2, planned for 100 South mid-block between West Temple and Main Street.

CCRI plans to construct only the lower-level retail portion of the building, perhaps as high as three stories, in the first phase to be completed by late 2010. The residential portion of what has been designed as a 19-story building will be added later as the housing market dictates, Bishop Burton said.

The developers want to see how quickly residences fill up before adding more units to the block. Depending on the market, the building's completion date will be somewhere between late 2010 and mid-2012.

"We hope we're able to (add the residential portion) right away," Bishop Burton said.

Parking structures on all three blocks of the project already are under construction, all of which are slated to be completed by summer 2009.

Construction on the 50,000-square-foot Harmons grocery store planned for 100 South between State Street and 200 East is set to begin this summer, with a late-2009 target for completion.

Also in 2009, the new food court will be open for business in the lower levels of the Key Bank tower on State Street. The existing food court on South Temple will remain open until the new 13-kitchen, 1,000-seat dining area begins serving customers.

Recent comments

I'm excited for the renovations. I live downtown and love it!...

downtowner | April 9, 2008 at 12:00 p.m.

When this is all finished I will NOT be able to afford the gas to...

By 2012? | March 19, 2008 at 8:40 p.m.

I like it

Comment | March 19, 2008 at 7:44 p.m.

LDS Church Presiding Bishop H. David Burton, left, and church spokesman Dale Bills give an update on City Creek construction to the City Council Tuesday. A video shows a proposed skybridge. (Danny Chan La, Deseret Morning News)
Danny Chan La, Deseret Morning News
LDS Church Presiding Bishop H. David Burton, left, and church spokesman Dale Bills give an update on City Creek construction to the City Council Tuesday. A video shows a proposed skybridge.