New I-80 bridges are all in place

Published: Thursday, July 31, 2008 12:06 a.m. MDT
E-MAIL | PRINT | FONT + - 
As drivers pass over I-80 on 1300 East they may notice that the once-full bridge farm is now empty. A week ahead of schedule, crews working along the interstate were able to move and lower into place seven multimillion-pound structures between Highland Drive and 300 East.

Crew members on-site Wednesday were relieved to see the project nearing completion, but their work on the interstate is far from complete, said John Montoya, site project manager. Workers have begun laying pavement along the five lanes added to the interstate and will soon be constructing noise walls.

"We're not home free yet — we're not even to the midpoint yet, which is the traffic shift onto the new road," Montoya said. "This was the biggest challenge that we've completed, but there is a lot left to build."

After the lane shift, which is expected in late fall, crews will begin replacing bridges along the eastbound section of the interstate, using conventional bridge-building techniques.

In the past, the Utah Department of Transportation has used rapid bridge-building techniques at 4500 South, but crews there drove the structure in from the side and lifted it into place. For this newly completed project, crews launched the bridges from the interstate and lowered them into place. It was a first in the nation and a learning experience, Montoya said.

Story continues below

Montoya estimated that it took crews five to seven days to move the Highland Drive structure from the bridge farm to its final location above the street. For the first move Montoya said crews intentionally took their time to get a grasp of the many aspects involved in transporting the structures. By the time UDOT moved the 300 East bridge, it took just 36 hours from the initial move to the placement.

"When you move seven bridges you have an opportunity to learn from each one and apply those lessons to each proceeding placement," Montoya said.

Wayne Bowden, project manager for Ralph Wadsworth Construction, said that the rapid bridge project was a test to see if this kind of building technique could be done. He believes the crews passed with flying colors. Bowden said he expects to see other projects like this in the state and nation.

"I'd just like to acknowledge how hard everyone has worked to get us to this point," Montoya said. "We've had 50 to 60 guys working their guts out every day."

The days were long and hot, crew members said Wednesday. Dennis Theis, a superintendent with Mammot, a Dutch company that provided equipment for the move, said that on average he logged about 95 hours a week, but he added, "The overtime is good for the mortgage."

The project was an inconvenient and intense time for area residents and motorists, Montoya conceded, but he expressed his thanks for the public patience as crews worked to complete the project.

Recent comments

My company has done a little work with Wadsworth in the past. We try...

Structural Engineer replies | Aug. 1, 2008 at 8:28 a.m.

Are you sure Mr. "Structural Engineer" isn't actually the PR guy. If...

Who Are the Crews | July 31, 2008 at 11:33 p.m.

Another reason is the bridge farm is on the wrong side of the freeway...

to why not eastbound | July 31, 2008 at 11:20 p.m.

UDOT crews move the Interstate-80/600 East bridge early Wednesday in Salt Lake City. Workers have moved seven new bridges into their places on the freeway between Highland Drive and 300 East. (Jeffrey D. Allred, Deseret News)
Jeffrey D. Allred, Deseret News

UDOT crews move the Interstate-80/600 East bridge early Wednesday in Salt Lake City. Workers have moved seven new bridges into their places on the freeway between Highland Drive and 300 East.

Latest comments

What school district in any state thinks they have too much money per pupil...

Utah fans, go back to your caves and enjoy your good season. The score is...

I have opposed Rep Cannon through three elections, and find Rep Chaffetz a...

Obama wants pork-free plan

Isn't Obama saying he will cut pork about the same as the fox guarding the...

Is this all you and the 1a fans have to do is sit and complain about rankings...

Obama wants pork-free plan

"Utah Infrastructure" has given us a wonderful testimony based on blind,...

The is an opportunity for BYU, that if they win, will set the tone for their...

'Wonderland' returns

All eight episodes were aired in Germany and the Scandinavian countries, so...

What Planet, I am talking parochial schools, not private schools. And I'm...

Obviously most of you do not know that Oly has 2 starters of which are both...

Advertisements