Plane repair costs shock Congress
Prices at Hill and 2 other A.F. bases doubled in 4 years
Prices have doubled in four years, from an average $120 an hour for labor and materials in 2000 to $238 an hour now charged by Hill's Ogden Air Logistics Center, the Oklahoma City Air Logistics Center and Warner Robins Air Logistics Center, Ga.
Because Air Force wings expect to request 20.8 million hours of in-house work this fiscal year, "customers will have to pay about $4.9 billion for work that they would have paid about $2.5 billion in fiscal year 2000," according to a new report by the U.S. General Accounting Office, a research arm of Congress.
As it faces a couple billion dollars in higher costs for such aircraft work, the House Appropriations Subcommittee on Defense asked the GAO to look independently into why prices are spiraling upward.
The GAO reports that it found that two-thirds of the increase come from higher costs the depots are paying for materials. It also gave the damning conclusion that the depots have been unable "to effectively identify the cause and take corrective actions, as appropriate, on (their) continuously upward spiraling material costs."
The GAO said the depots and Air Force have tried some steps to control the costs, but "management has been unable to clearly show that the benefits of the initiatives exceed their costs."
In response to the report, the Defense Department wrote that the Air Force is improving its cost accounting systems and is reviewing data to see if more corrective action is needed and will brief the secretary of defense quarterly on updates.
The three air logistics centers rely on sales, instead of direct congressional appropriations, to finance their operations. They are supposed to charge customer Air Force wings exactly what it costs them to repair and overhaul aircraft, missiles and component parts. They are supposed to break even financially over time.
The GAO complained the Air Force did not always follow that directive, which has caused some of the recent problems.
From 2000 to 2003, "Prices that the depot maintenance activity group charged customers were not set high enough to recover the group's reported costs of performing the work," resulting in a loss over that time of $1.1 billion, the report said.
The GAO said the Air Force forced the depots to hold prices artificially low during that time, in part, to help ensure that "customers would be able to get the needed work done with the amount of funds provided them through the budget process."




You can be the first to comment on this story.