U.S. 6 reopening
A major, concerted effort refills blast crater and removes debris
The 35-foot deep crater in the highway? Nearly filled.
The road will be open this morning, less than 48 hours after the blast occurred.
"I think it's another example of how Utahns can pull together in a crisis situation and make things happen," said Nile Easton, spokesman for the Utah Department of Transportation. "When we get our back up to the wall, we can do amazing things."
About 2 p.m. on Thursday, Easton was standing about a quarter-mile from the blast site, watching as crews hauled dirt up the canyon, dumped it, then removed debris. UDOT officials were first allowed on the site about 4 p.m. on Wednesday. By 10 p.m. Wednesday, crews had begun the tedious process of hauling dirt and removing debris.
Less than 20 hours later, crews were waiting to begin paving operations. In total, about 4,500 tons of gravel were used to fill the crater. About 350 loads were taken up the canyon.
The fact that fill work was nearly done within 24 hours of the explosion, said Easton, is a testament to quick action by volunteers and a joint effort with contractors and the state. When work is completed this morning, it will be permanent, he said.
Seventeen UDOT snowplow trucks were used to haul fill material. Staker Paving and Construction provided other heavy equipment including backhoes, tractors and asphalt.
Tracy Conti, UDOT Region 3 director, said no major road projects were delayed by the shuffling of UDOT equipment and workers to the blast site. Workers who were offered overtime pay were taken from small maintenance projects, he said. The snowplow trucks were not being used at other sites.
As for the cost of repairs, contingency money in UDOT's maintenance budget will be used to pay the contractor. Efforts are being made to seek reimbursement for costs through insurance.
"My supervisors are very, very good at economically doing some amazing things," said Conti. "They love it when they get a situation like this a real project where there is a lot to do in a short amount of time."
One of the primary challenges UDOT faced was damage to the sandstone wall on the north side of the road. The blast jarred several large boulders loose, so a track-hoe was used to knock them loose, then jackhammers to break them up.
At the work site, crews and machinery were working in a tight area, something that made the job difficult, said Easton. Officials were also on-site from the U.S. Forest Service, railroad and fiber-optic companies.




You can be the first to comment on this story.